Mike Roberson

Mike Roberson

Tuesday, 02 February 2016 13:43

Boar's Head

Project Name: GMP Plant Upgrades / Cook Tank Project / Plant Layout Modification / Plant Maintenance

Location: Petersburg, VA / Jarret, VA

Preformed Work For: Boar’s Head

Merritt Piping & Fabrication Inc. Performed: Install Sanitary System Upgrade / Smoke House Ovens / CIP Systems / Conveyors / Box Shoots / Maintenance.

 

Tuesday, 02 February 2016 13:43

Sandoz

Project Name: Cooling Tower Replacement Project

Location: Wilson, NC

Preformed Work For: Xenergy

Merritt Piping & Fabrication Inc. Performed: Removed & Replaced Three Cooling Towers & Structural Steel / Equalizer Piping / Filter Systems / Supply & Return Lines.

 

Tuesday, 02 February 2016 13:42

Ashland

Project Name: Chemical Dissolution Building

Location: Hopewell, VA

Preformed Work For: Alliance Energy 

Merritt Piping & Fabrication Inc. Performed: Install Process Equipment / Process Tanks / Process Piping / Mechanical Piping / Install Process Conveyors / Monorail System / Structural Steel. 

 

Page 3 of 6